Flood Control and Drainage25C00354

SUSTAINABLE INFRA. PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF RIVER SLOPE PROTECTION STRUCTURE ALONG BULO RIVER(SEGMENT A),PUROK 6, BRGY. LAMBAKIN,SAN MIGUEL, BULACAN

SUSTAINABLE INFRA. PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF RIVER SLOPE PROTECTION STRUCTURE ALONG BULO RIVER(SEGMENT A),PUROK 6, BRGY. LAMBAKIN,SAN MIGUEL, BULACAN is a DPWH-tracked public work in Bulacan 3rd DEO, Region III. Reported contract value: ₱95,099,981.00. Status: Past target date (DPWH On-Going). Contractor on record: 11-16 CONST. Figures trace to dpwh.

Bulacan 3rd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Meycauayan River and its tributaries (Deca Homes Section), Barangay Saluysoy, Meycauayan City, Bulacan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-CAR-25-0008445

₱4,870,231.00 · FY2025

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

244 projects · ₱19.8B total · 0 flags

4. Implementation

Contract Amount

₱95,099,981.00

Progress

Past target date (DPWH On-Going)

Start Date

March 14, 2025

Target End

January 7, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.