CONSTRUCTION OF DPWH-MAGUINDANAO 2ND DEO BUILDING (PHASE II), BULUAN, MAGUINDANAO

CONSTRUCTION OF DPWH-MAGUINDANAO 2ND DEO BUILDING (PHASE II), BULUAN, MAGUINDANAO is a DPWH-tracked public work in Region XII, Region XII. Reported contract value: ₱63,374,994.47. Status: Reported complete (DPWH). Contractor on record: GEMMA CONST SUPPLY INC FORMERLY:GEMMA CON. Figures trace to dpwh.

Region XII, Region XII
Region: Region XII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱63,374,994.47

Progress

Reported complete (DPWH)

Start Date

October 23, 2016

Target End

February 14, 2018