Roads22J00072

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ZAMBOANGA CITY BY-PASS ROAD (WEST COAST SECTION), PHASE II

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ZAMBOANGA CITY BY-PASS ROAD (WEST COAST SECTION), PHASE II is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱94,385,041.02. Status: Past target date (DPWH On-Going). Contractor on record: WBUILD CONST CORP FORMERLY: WEE BUILDERS. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2022 GAA. DBM GAA FY2022

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱94,385,041.02

Progress

Past target date (DPWH On-Going)

Start Date

March 21, 2022

Target End

June 30, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.