Roads20CC0165

ASPHALT OVERLAY OF VARIOUS MUNICIPAL ROADS WITHIN THE BALIUAG, BULACAN

ASPHALT OVERLAY OF VARIOUS MUNICIPAL ROADS WITHIN THE BALIUAG, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱47,518,454.97. Status: Reported complete (DPWH). Contractor on record: PHILIPPINE CHEMSTEEL INDUSTRIES INC. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱48,594,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structures along Angat River, Makinabang Section, Sta. 00+000 to Sta. 00+353.60, Baliuag, Bulacan
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-NCR-20-0007526

₱1,558,081.00 · FY2020

Released to Muntinlupa Business High School (Pedro E. Diaz High School-Buli Annex) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

368 projects · ₱14.1B total · 0 flags

Other projects by this contractor

No sat.

SPECIAL ROAD FUND- MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239, INSTALLATION OF ROAD SAFETY DEVICES ALONG AGOO-BAGUIO CITY ROAD K0237+700 - K0237+800, K0247+500 - K0247+600, K0251+050 - K0251+150, K0251+300 - K0251+400, K0252+350 - K0252+600, K02

Region I, Region I

2023₱241.2M
Reported complete (DPWH)
No sat.

ACTIVE TRANSPORT BIKE SHARE SYSTEM AND SAFE PATHWAYS PROGRAM IN METROPOLITAN AREAS - EXPANSION OF ACTIVE TRANSPORT INFRASTRUCTURE

National Capital Region, National Capital Region

2022₱195.6M
Reported complete (DPWH)
No sat.

SPECIAL ROAD FUND- MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239, INSTALLATION OF ROAD SAFETY DEVICES ALONG PANGASINAN-NUEVA VIZCAYA ROAD, PACKAGE 1, PANGASINAN

Region I, Region I

2024₱193.0M
Reported complete (DPWH)
No sat.

SPECIAL ROAD FUND- MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239, INSTALLATION OF ROAD SAFETY DEVICES ALONG A) URDANETA JCT-DAGUPAN RD- K0201+000-K0201+370, K0201+370-K0201+870, K0201+870-K0202+000, K0202+000-K0203+021, K0203+021-K0203+947, K0203+9

Region I, Region I

2023₱193.0M
Reported complete (DPWH)
No sat.

SPECIAL ROAD FUND- MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239, INSTALLATION OF ROAD SAFETY DEVICES ALONG A) JUDGE JOSE DE VENECIA SR. AVE - K0207+(-711) - K0207+(-611), K0207+(-611) - K0207+000, K0207+000 - K0207+073, K0207+183 - K0207+374, K020

Region I, Region I

2023₱193.0M
Reported complete (DPWH)
No sat.

SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A 11239, INSTALLATION OF ROAD SAFETY DEVICES ALONG A) SN CARLOS-CALASIAO RD- K0211 + 000 - K0212 + 000, K0212 + 000 - K0212 + 471, K0212 + 560 - K0212 + 696, K0212 + 696 - K0212 + 775, K021

Region I, Region I

2023₱192.9M
Reported complete (DPWH)
View all 368 projects →

4. Implementation

Contract Amount

₱47,518,454.97

Progress

Reported complete (DPWH)

Start Date

November 26, 2020

Target End

January 24, 2021

5. Audit