Flood Control and Drainage25KL0023

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AMOROS RIVER (DOWNSTREAM OF AMOROS BR.), PACKAGE 1, EL SALVADOR, MISAMIS ORIENTAL

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AMOROS RIVER (DOWNSTREAM OF AMOROS BR.), PACKAGE 1, EL SALVADOR, MISAMIS ORIENTAL is a DPWH-tracked public work in Misamis Oriental 2nd DEO, Region X. Reported contract value: ₱70,074,886.43. Status: Past target date (DPWH On-Going). Contractor on record: 5S DEVELOPMENT CORP. Figures trace to dpwh.

Misamis Oriental 2nd DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Buncalalan River, Taboc Section (Package 1), Opol, Misamis Oriental
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-25-0016547

₱218,629.00 · FY2025

Released to Davao de Oro State College (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱70,074,886.43

Progress

Past target date (DPWH On-Going)

Start Date

February 13, 2025

Target End

December 1, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.