Buildings and Facilities19K00284

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MALADIG, PICONG, LANAO DEL SUR

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MALADIG, PICONG, LANAO DEL SUR is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱2,778,530.21. Status: Reported complete (DPWH). Contractor on record: SMA BUILDER. Figures trace to dpwh.

Region X, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱2,778,530.21

Progress

Reported complete (DPWH)

Start Date

September 23, 2019

Target End

January 5, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.