CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF WASIG RIVER CONTROL STRUCTURE, BARANGAY WASIG, MANSALAY, ORIENTAL MINDORO

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF WASIG RIVER CONTROL STRUCTURE, BARANGAY WASIG, MANSALAY, ORIENTAL MINDORO is a DPWH-tracked public work in Southern Mindoro DEO, Region IV-B. Reported contract value: ₱29,044,880.17. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: LEWIS GJANN CONST 54135. Figures trace to dpwh.

Southern Mindoro DEO, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Balite River Flood Control Structure, Barangay M. Adriatico, Gloria, Oriental Mindoro
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROII-25-0012843

₱1,000,000.00 · FY2025

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱29,044,880.17

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 25, 2025

Target End

November 27, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.