Roads15CJ0164

LIP, CONCRETING OF ROAD, BRGY. BALAYANG (GOING TO BATANG-BATANG, VICTORIA) VICTORIA, TARLAC 2ND LD

LIP, CONCRETING OF ROAD, BRGY. BALAYANG (GOING TO BATANG-BATANG, VICTORIA) VICTORIA, TARLAC 2ND LD is a DPWH-tracked public work in Tarlac DEO, Region III. Reported contract value: ₱2,671,226.09. Status: Reported complete (DPWH). Contractor on record: JAM-C BUILDERS 32870. Figures trace to dpwh.

Tarlac DEO, Region III
Region: Region III

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱2,671,226.09

Progress

Reported complete (DPWH)

Start Date

January 21, 2016

Target End

March 20, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.