Flood Control and Drainage25LE0038

CONSTRUCTION OF SEAWALL, BARANGAY OGPAO, STA. MARIA, DAVAO OCCIDENTAL

CONSTRUCTION OF SEAWALL, BARANGAY OGPAO, STA. MARIA, DAVAO OCCIDENTAL is a DPWH-tracked public work in Davao Occidental DEO, Region XI. Reported contract value: ₱4,946,998.58. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: ADAN BUILDERS CO. Figures trace to dpwh.

Davao Occidental DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control (Concrete Revetment) at Sta. Maria, Davao Occidental
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXII-25-0011195

₱329,000.00 · FY2025

Released to Kisante National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,946,998.58

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 21, 2025

Target End

June 4, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.