GAA 2025 SSP25MB0035

CONSTRUCTION OF ROAD WITH DRAINAGE INCLUDING FACILITIES FROM JUNCTION DIGOS MAKAR ROAD TO ALBERT MORROW BLVD. (NLSA ROAD), GENERAL SANTOS CITY, SOUTH COTABATO

CONSTRUCTION OF ROAD WITH DRAINAGE INCLUDING FACILITIES FROM JUNCTION DIGOS MAKAR ROAD TO ALBERT MORROW BLVD. (NLSA ROAD), GENERAL SANTOS CITY, SOUTH COTABATO is a DPWH-tracked public work in South Cotabato 1st DEO, Region XII. Reported contract value: ₱70,170,187.91. Status: Past target date (DPWH On-Going). Contractor on record: SARANGANI ROCKMIXER INC FORMERLY:SARANGANI ROCKMIXER. Figures trace to dpwh.

South Cotabato 1st DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Possible match · score 75%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control/Protection Work of Dam, Tam-is Communal Irrigation System, Maasin City, Southern Leyte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-25-0017864

₱31,597,080.00 · FY2025

Released to Division of Lucena City (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱70,170,187.91

Progress

Past target date (DPWH On-Going)

Start Date

March 19, 2025

Target End

December 31, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.