Flood Control and Drainage16OD0026

CONSTRUCTION OF FLOOD CONTROL WALL ALONG TULLAHAN RIVER (STA. 1+000 TO STA. 1+383), VALENZUELA CITY, 2ND LD

CONSTRUCTION OF FLOOD CONTROL WALL ALONG TULLAHAN RIVER (STA. 1+000 TO STA. 1+383), VALENZUELA CITY, 2ND LD is a DPWH-tracked public work in Metro Manila 3rd DEO, National Capital Region. Reported contract value: ₱17,675,529.36. Status: Reported complete (DPWH). Contractor on record: FRAMECON BUILDERS 22482. Figures trace to dpwh.

Metro Manila 3rd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱17,675,529.36

Progress

Reported complete (DPWH)

Start Date

March 23, 2016

Target End

August 19, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.