Roads22OH0050

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-TERTIARY ROADS-PASIG LINE (SO2838LZ) CHAINAGE 107-CHAINAGE 671, MANILA

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-TERTIARY ROADS-PASIG LINE (SO2838LZ) CHAINAGE 107-CHAINAGE 671, MANILA is a DPWH-tracked public work in South Manila DEO, National Capital Region. Reported contract value: ₱11,150,964.39. Status: Reported complete (DPWH). Contractor on record: ELITE GEN CONTRACTOR AND DEVELOPMENT CORP. Figures trace to dpwh.

South Manila DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 77%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structures and Facilities along Earnshaw St., (Estero de San Miguel to A.H. Lacson Ave.) and Antipolo St., (G. Tuazon to Espana Blvd.), Manila City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXII-22-0000752

₱12,780,000.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

121 projects · ₱7.5B total · 3 flags

Other projects by this contractor

Construction of Road Dike along Bucayao River (East Side), Sitio Malinao Section, Barangay Tagumpay, Naujan, Oriental Mindoro

NAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B

2024₱247.5M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUSUANGA RIVER, BRGY. SAN PEDRO (DOWNSTREAM), SAN JOSE, OC

Region IV-B, Region IV-B

2024₱232.4M
Past target date (DPWH On-Going)
No sat.

OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST./ REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF LOBOC RIVER CONTROL STRUCTURE, VILLAFLOR SECTION, LOBOC, BOHOL

Region VII, Region VII

2023₱213.9M
Past target date (DPWH On-Going)
No sat.

OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST./ REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF LOBOC RIVER CONTROL STRUCTURE, CANLASID SECTION, LOBOC, BOHOL

Region VII, Region VII

2023₱193.0M
Past target date (DPWH On-Going)

Construction of Road Dike along Mag-asawang Tubig River, Sitio Dike, Barangay Apitong Section, Naujan, Oriental Mindoro

NAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B

2024₱193.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY HINOLASO, DOLORES, EASTERN SAMAR

Region VIII, Region VIII

2024₱190.9M
Past target date (DPWH On-Going)
View all 121 projects →

4. Implementation

Contract Amount

₱11,150,964.39

Progress

Reported complete (DPWH)

Start Date

April 7, 2022

Target End

May 6, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.