GAA 2025 OO-225ME0060

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BADTASAN, KIAMBA, SARANGANI PROVINCE

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BADTASAN, KIAMBA, SARANGANI PROVINCE is a DPWH-tracked public work in Sarangani DEO, Region XII. Reported contract value: ₱65,448,907.10. Status: Past target date (DPWH On-Going). Contractor on record: CHARIFER BUILDERS INC. Figures trace to dpwh.

Sarangani DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Lagundi, Kiamba, Sarangani
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-25-0014631

₱2,983,776.00 · FY2025

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱65,448,907.10

Progress

Past target date (DPWH On-Going)

Start Date

March 31, 2025

Target End

December 22, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.