Buildings and Facilities19MF0028

CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING (NEW BRGY. HALL) AT BRGY. BUENAFLOR, TACURONG CITY, SULTAN KUDARAT.

CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING (NEW BRGY. HALL) AT BRGY. BUENAFLOR, TACURONG CITY, SULTAN KUDARAT. is a DPWH-tracked public work in Sultan Kudarat 1st DEO, Region XII. Reported contract value: ₱1,474,117.26. Status: Reported complete (DPWH). Contractor on record: CS CONST AND SUPPLY INC FORMERLY: CS CONST AND SUPPLY. Figures trace to dpwh.

Sultan Kudarat 1st DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROII-19-0019346

₱104,000.00 · FY2019

Released to Quezon National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

246 projects · ₱4.5B total · 10 flags

4. Implementation

Contract Amount

₱1,474,117.26

Progress

Reported complete (DPWH)

Start Date

June 17, 2019

Target End

August 15, 2019

5. Audit