Roads18CJ0148

NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF BY-PASS AND DIVERSION ROADS ROMULO HIGHWAY TO MNR VIA FAIRLANE BYPASS/ DIVERSION ROAD, INCL. DRAINAGE, TARLAC

NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF BY-PASS AND DIVERSION ROADS ROMULO HIGHWAY TO MNR VIA FAIRLANE BYPASS/ DIVERSION ROAD, INCL. DRAINAGE, TARLAC is a DPWH-tracked public work in Tarlac DEO, Region III. Reported contract value: ₱46,549,361.75. Status: Reported complete (DPWH). Contractor on record: L S D CONST. Figures trace to dpwh.

Tarlac DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱46,549,361.75

Progress

Reported complete (DPWH)

Start Date

May 21, 2018

Target End

May 18, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.