Flood Control and Drainage25BH0198

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF LABINAB FLOOD CONTROL STRUCTURE, STA. 0+000 - STA. 0+

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF LABINAB FLOOD CONTROL STRUCTURE, STA. 0+000 - STA. 0+ is a DPWH-tracked public work in Isabela 4th DEO, Region II. Reported contract value: ₱93,600,459.82. Status: Past target date (DPWH On-Going). Contractor on record: DALCON CONST. Figures trace to dpwh.

Isabela 4th DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱100,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Caquilinan Flood Control Structure, Section 1, Cordon, Isabela
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-25-0017562

₱-1,460,337.00 · FY2025

Released to Rizal Medical Center (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱93,600,459.82

Progress

Past target date (DPWH On-Going)

Start Date

June 5, 2025

Target End

July 24, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.