Bridges24DM0133

CONSTRUCTION OF BRIDGE, BARANGAY SAN IGNACIO ILAYA AND BARANGAY SAN NICOLAS, MUNICIPALITY OF GENERAL LUNA, QUEZON, GENERAL LUNA, QUEZON

CONSTRUCTION OF BRIDGE, BARANGAY SAN IGNACIO ILAYA AND BARANGAY SAN NICOLAS, MUNICIPALITY OF GENERAL LUNA, QUEZON, GENERAL LUNA, QUEZON is a DPWH-tracked public work in Quezon 3rd DEO, Region IV-A. Reported contract value: ₱4,950,000.00. Status: Reported complete (DPWH). Contractor on record: MURIELEVEN BUILDERS AND CONST SUPPLY CORP. Figures trace to dpwh.

Quezon 3rd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Brgy. Cabuyao, Padre Burgos, Quezon
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-24-0019593

₱20,000,000.00 · FY2024

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

192 projects · ₱1.6B total · 5 flags

Other projects by this contractor

View all 192 projects →

4. Implementation

Contract Amount

₱4,950,000.00

Progress

Reported complete (DPWH)

Start Date

May 20, 2024

Target End

January 14, 2025

5. Audit