Roads24P00043

CONSTRUCTION OF MONTABIONG, LAGAWE TO BANAO & ANABA, BANAUE ACCESS ROADTINOC, IFUGAO

CONSTRUCTION OF MONTABIONG, LAGAWE TO BANAO & ANABA, BANAUE ACCESS ROADTINOC, IFUGAO is a DPWH-tracked public work in Cordillera Administrative Region, Cordillera Administrative Region. Reported contract value: ₱9,900,000.00. Status: Past target date (DPWH On-Going). Contractor on record: PAULA MAE BUHONG CONST. Figures trace to dpwh.

Cordillera Administrative Region, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

21 projects · ₱479.7M total · 0 flags

Other projects by this contractor

No sat.

RD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL RD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED RD STDS (HDM-4 PROJECT ANALYSIS), KIANGAN-TINOC-BUGUIAS RD, CHAINAGE 43087-CHAINAGE 44907, CHAINAGE 45668 - CHAINAGE 46347, TINOC, IFUGAO

Cordillera Administrative Region, Cordillera Administrative Region

2016₱97.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION / IMPROVEMENT OF ACCESS ROAD LEADING TO DECLARED TOURIST DESTINATION - KINAKIN - CAMBULO ROAD LEADING TO KINAKIN & CAMBULO NATIVE VILLAGES RICE TERRACES, BANAO RICE TERRACES

Ifugao 2nd DEO, Cordillera Administrative Region

2017₱60.5M
Past target date (DPWH On-Going)
No sat.

LAGAWE-HINGYON ROAD VIA BURNAY LEADING TO MT. ATUGO AND OTHER TOURISM DESTINATIONS, LAGAWE AND HINGYON, IFUGAO

Ifugao 1st DEO, Cordillera Administrative Region

2023₱49.0M
Reported complete (DPWH)
No sat.

REHABILITATION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG KIANGAN - TINOC - BUGUIAS ROAD, K0354+200 - K0354+500, GUMHANG, TINOC, IFUGAO

Cordillera Administrative Region, Cordillera Administrative Region

2023₱47.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-SECONDARY ROADS-NUEVA VIZCAYA-IFUGAO-MT. PROVINCE RD. - K0317+667, LAGAWE, IFUGAO

Ifugao 1st DEO, Cordillera Administrative Region

2025₱40.5M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-SECONDARY ROADS-NUEVA VIZCAYA-IFUGAO-MT. PROVINCE RD. - K0316+940, K0317+260, K0317+914-K0317+982, LAGAWE, IFUGAO

Ifugao 1st DEO, Cordillera Administrative Region

2025₱33.2M
Past target date (DPWH On-Going)
View all 21 projects →

4. Implementation

Contract Amount

₱9,900,000.00

Progress

Past target date (DPWH On-Going)

Start Date

July 29, 2024

Target End

April 8, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.