Buildings and Facilities22AA0083

CONSTRUCTION (COMPLETION) OF MULTI PURPOSE BUILDING, BARANGAY 26 SAN MARCELINO, LAOAG CITY, ILOCOS NORTE

CONSTRUCTION (COMPLETION) OF MULTI PURPOSE BUILDING, BARANGAY 26 SAN MARCELINO, LAOAG CITY, ILOCOS NORTE is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱1,930,980.68. Status: Reported complete (DPWH). Contractor on record: JCA CONST AND CONST SUPPLY. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱12,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure Along Laoag River Basin, Brgy. San Marcos, Sarrat, Ilocos Norte
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROI-22-0012240

₱250,066.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

133 projects · ₱2.4B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, GUMACA-PITOGO-MULANAY-SN. NARCISO RD., K0202+745 - K0206+531, GUMACA,

Quezon 4th DEO, Region IV-A

2025₱93.4M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS, QUIRINO HIGHWAY, K0253+000 - K0254+209, GUINAYANGAN, QUEZON

Quezon 4th DEO, Region IV-A

2025₱93.1M
Reported complete (100% progress, DPWH status On-Going)
No sat.

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - MANILA NORTH ROAD - K0578+645 - K0578+700, PAGUDPUD, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2021₱92.6M
Reported complete (DPWH)

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MALING RIVER, ATIMONAN, QU

Quezon 4th DEO, Region IV-A

2025₱90.0M
Reported complete (100% progress, DPWH status On-Going)

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SEAWALL ALONG BURGOS BAY, BRGY. BOBON SECTION AND BRGY. PAAYAS SECTION, MUNICIPALITY OF BURGOS, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2022₱86.8M
Reported complete (DPWH)

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BISLAK RIVER, BRGY. DIPILAT, MUNICIPALITY OF VINTAR, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2022₱85.9M
Reported complete (DPWH)
View all 133 projects →

4. Implementation

Contract Amount

₱1,930,980.68

Progress

Reported complete (DPWH)

Start Date

March 30, 2022

Target End

June 7, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.