Buildings and Facilities17HC0074

CONSTRUCTION OF 1-STOREY/2CL, 7.00M X 18.00M (MAINLAND) AT EUGENIO V. AMORES MHS (REGULAR WORKSHOP), SAGBAYAN, BOHOL

CONSTRUCTION OF 1-STOREY/2CL, 7.00M X 18.00M (MAINLAND) AT EUGENIO V. AMORES MHS (REGULAR WORKSHOP), SAGBAYAN, BOHOL is a DPWH-tracked public work in Bohol 2nd DEO, Region VII. Reported contract value: ₱2,508,978.51. Status: Reported complete (DPWH). Contractor on record: SLP CONST. Figures trace to dpwh.

Bohol 2nd DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Improvement of Inabanga Flood Control (Brgys. Ondol and Bugang), Inabanga, Bohol
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-17-0018206

₱216,240.00 · FY2017

Released to Catanduanes State Rel University emp (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

92 projects · ₱943.8M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS-CATIGBIAN-CANMANO ROAD(CATIGBIAN SECTION) LEADING TO SAGBAYAN PEAK, CHOCOLATE HILLS AND DANAO ADVENTURE PARK, CATIGBIAN, BOHOL

Bohol 1st DEO, Region VII

2018₱47.0M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-SECONDARY ROADS JCT (LIR) CARMEN-SAGBAYAN- BACANI RD- K0178+765 - K0178+804, SAGBAYAN, BOHOL

Bohol 2nd DEO, Region VII

2023₱31.2M
Reported complete (DPWH)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES - LA PAZ (CORTES) - CABAGUAN - LOURDES - ANISLAG (CORELLA) ROAD IN SUPPORT OF THE AGRIBUSINESS INDUSTRY, CORTES, BOHOL

Bohol 1st DEO, Region VII

2022₱29.4M
Reported complete (DPWH)
No sat.

INSTALLATION OF ROAD SAFETY DEVICES (SOLAR PAVEMENT STUDS) - JCT. (TER) DAUIS-PANGLAO ROAD - K0003+(-776) - K0003+000 (S00020BH), K0003+000 - K0018+084

Bohol 1st DEO, Region VII

2022₱29.3M
Reported complete (DPWH)
No sat.

CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAIN WATER COLLECTORS, WATER SUPPLY SYSTEM- CONSTRUCTION OF WATERWORKS SYSTEMS (LEVEL 3), BUENAVISTA, BOHOL

Bohol 2nd DEO, Region VII

2023₱28.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES -REHABILITATION OF SAN ISIDRO- CATIGBIAN VI

Bohol 2nd DEO, Region VII

2022₱28.6M
Reported complete (DPWH)
View all 92 projects →

4. Implementation

Contract Amount

₱2,508,978.51

Progress

Reported complete (DPWH)

Start Date

January 9, 2018

Target End

April 3, 2018

5. Audit