Buildings and Facilities19HH0007

LOCAL PROGRAM: LOCAL INFRASTRUCTURE PROGRAM - BUILDINGS AND OTHER STRUCTURE - SCHOOL BUILDING - REHABILITATION (COMPLETION) OF SCHOOL BUILDING, HIPODROMO ELEMENTARY SCHOOL, BRGY. HIPODROMO, CEBU CITY

LOCAL PROGRAM: LOCAL INFRASTRUCTURE PROGRAM - BUILDINGS AND OTHER STRUCTURE - SCHOOL BUILDING - REHABILITATION (COMPLETION) OF SCHOOL BUILDING, HIPODROMO ELEMENTARY SCHOOL, BRGY. HIPODROMO, CEBU CITY is a DPWH-tracked public work in Cebu City DEO, Region VII. Reported contract value: ₱978,083.53. Status: Reported complete (DPWH). Contractor on record: E V CABALLERO CONST. Figures trace to dpwh.

Cebu City DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-19-0011181

₱6,992,000.00 · FY2019

Released to Regional Science High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

27 projects · ₱96.8M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF CONCRETE BRIDGE, SITIO CAMPO,

Cebu City DEO, Region VII

2024₱14.7M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE CONSTRUCTION OF FLOOD CONTROL STRUCTURES AT PAMINTAO RIVER ALONG CEBU NORTH HAGNAYA WHARF ROAD, BARANGAY TAYTAYAN, CITY OF BOGO

Cebu 4th DEO, Region VII

2018₱9.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD, PACKAGE 2, BARANGAY LABA

Cebu City DEO, Region VII

2025₱9.7M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/FACILITIES-ROAD CONCRETING, BRGY. LABANGON, CEBU CITY, C

Cebu City DEO, Region VII

2023₱9.6M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BRGY. LABANGON, CEBU CITY

Cebu City DEO, Region VII

2020₱5.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF 2-UNITS UNIQUE WORKSHOP BUILDING, DOÑA LILING NEIS NEGAPATAN NHS, TABOGON, CEBU

Cebu 4th DEO, Region VII

2017₱5.2M
Reported complete (DPWH)
View all 27 projects →

4. Implementation

Contract Amount

₱978,083.53

Progress

Reported complete (DPWH)

Start Date

July 31, 2019

Target End

September 13, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.