Buildings and Facilities24F00426

CAPITAL OUTLAY - DOH HEALTH FACILITIES ENHANCEMENT PROGRAM (HFEP) - CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - GUBAT SUPER HEALTH CENTER, SORSOGON, GUBAT, SORSOGON (2ND LEGISLATIVE DISTRICT)

CAPITAL OUTLAY - DOH HEALTH FACILITIES ENHANCEMENT PROGRAM (HFEP) - CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - GUBAT SUPER HEALTH CENTER, SORSOGON, GUBAT, SORSOGON (2ND LEGISLATIVE DISTRICT) is a DPWH-tracked public work in Region V, Region V. Reported contract value: ₱11,817,960.11. Status: Past target date (DPWH On-Going). Contractor on record: GOLDEN TILLER CONST AND SUPPLY. Figures trace to dpwh.

Region V, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

39 projects · ₱585.1M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-REHAB/IMPROVEMENT OF FLOOD CONTROL STRUCTURES ALONG CABILOGAN RIVER, SAN AGUS

Region V, Region V

2024₱141.1M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURES IN SUPPORT OF NATIONAL SECURITY (TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM-TIKAS)-CONSTRUCTION OF 5RCDG, ARESCOM TWO(2) STOREY BILLETING FACI

Region V, Region V

2025₱29.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/REHABILITATION /IMPROVEMENT OF FACILITIES FOR PERSONS WITH DISABILITIES (PWD) AND ELDERLIES/SENIOR CITIZENS,INCLUDING GENDER-RESPONSIVE FACILITIES-REGION V

Region V, Region V

2022₱28.1M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - TRAVESIA BR. 1(B00317LZ) ALONG DAANG MAHARLIKA (LZ), GUINOBATAN, ALBAY 3RD LEGISLATIVE DISTRICT

Region V, Region V

2022₱24.5M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURES IN SUPPORT OF NATIONAL SECURITY (TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM-TIKAS)-RENOVATION OF CAMP OLA LIAISON OFFICE,LEGAZPI CITY, ALBAY

Region V, Region V

2021₱24.1M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF TECHNOLOGY AND ENGINEERING BUILDING (FORMER BOY'S TRADE BUILDING), SIPOCOT CAMPUS, PHASE I - CENTRAL BICOL STATE UNIVERSITY OF AGRICULTURE, SIPOCOT, CAMARINES SUR

Region V, Region V

2024₱19.7M
Past target date (DPWH On-Going)
View all 39 projects →

4. Implementation

Contract Amount

₱11,817,960.11

Progress

Past target date (DPWH On-Going)

Start Date

September 20, 2024

Target End

June 6, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.