Roads22KF0094

ROAD CONCRETING OF NELLITA Q. NOVAL, MUNICIPAL ACCESS ROAD AT BRGY. POBLACION TO BRGY. SAN ANTONIO, PHASE II, TUBOD, LANAO DEL NORTE

ROAD CONCRETING OF NELLITA Q. NOVAL, MUNICIPAL ACCESS ROAD AT BRGY. POBLACION TO BRGY. SAN ANTONIO, PHASE II, TUBOD, LANAO DEL NORTE is a DPWH-tracked public work in Lanao del Norte 1st DEO, Region X. Reported contract value: ₱4,950,000.00. Status: Reported complete (DPWH). Contractor on record: INSTA BUILDERS. Figures trace to dpwh.

Lanao del Norte 1st DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Iligan River, Barangay Tubod, Iligan City, Lanao del Norte
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXI-22-0013666

₱6,300.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱4,950,000.00

Progress

Reported complete (DPWH)

Start Date

March 24, 2022

Target End

May 25, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.