Construction of Flood Mitigation Structure21IC0043

Construction/Rehabilitation of Flood Control Mitigation Facilities along Mainit River, Phase 3, Brgy. Cavite, Alangalang, Leyte

Construction/Rehabilitation of Flood Control Mitigation Facilities along Mainit River, Phase 3, Brgy. Cavite, Alangalang, Leyte is a DPWH-tracked public work in LEYTE, Region VIII. Reported contract value: ₱49,000,000.00. Status: Reported complete (DPWH). Contractor on record: ED1SON DEVELOPMENT & CONST INC / MILES CONST AND ENT. Figures trace to sumbong.

LEYTE, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Rehabilitation of Flood Control Mitigation Facilities along Mainit River, Phase 3, Brgy. Cavite, Alangalang, Leyte
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVA-21-0008181

₱74,106,000.00 · FY2021

Released to Laguna 1st District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0010265

₱115,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0005378

₱76,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0008586

₱50,000,000.00 · FY2021

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱49.0M total · 0 flags

4. Implementation

Contract Amount

₱49,000,000.00

Progress

Reported complete (DPWH)

Start Date

November 11, 2021

Target End

July 28, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.