Buildings and Facilities19JG0116

CONSTRUCTION OF MULTI-PURPOSE COVERED COURT AT SAN PABLO NATIONAL HIGH SCHOOL, POBLACION, SAN PABLO, ZAMBOANGA DEL SUR

CONSTRUCTION OF MULTI-PURPOSE COVERED COURT AT SAN PABLO NATIONAL HIGH SCHOOL, POBLACION, SAN PABLO, ZAMBOANGA DEL SUR is a DPWH-tracked public work in Zamboanga del Sur 2nd DEO, Region IX. Reported contract value: ₱4,849,962.38. Status: Reported complete (DPWH). Contractor on record: M S CONST AND MARKETING 9762. Figures trace to dpwh.

Zamboanga del Sur 2nd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱4,849,962.38

Progress

Reported complete (DPWH)

Start Date

August 2, 2019

Target End

February 9, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.