Roads20HF0044

CONSTRUCTION/IMPROVEMENT OF BRGY. BUNGA-LAMAC-POBLACION ROAD LEADING TO RESORT AND CAVE, TOLEDO CITY-PINAMUNGAHAN, CEBU

CONSTRUCTION/IMPROVEMENT OF BRGY. BUNGA-LAMAC-POBLACION ROAD LEADING TO RESORT AND CAVE, TOLEDO CITY-PINAMUNGAHAN, CEBU is a DPWH-tracked public work in Cebu 3rd DEO, Region VII. Reported contract value: ₱4,899,841.32. Status: Reported complete (DPWH). Contractor on record: BL PANGAN CONST 25158. Figures trace to dpwh.

Cebu 3rd DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROV-20-0015559

₱2,088,220.00 · FY2020

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱4,899,841.32

Progress

Reported complete (DPWH)

Start Date

October 13, 2020

Target End

December 26, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.