REHABILITATION OF TOLEDO-TABUELAN-SAN REMEGIO ROAD (INTERMITTENT SECTION) WITH SLIPS, LOCATED AT (1) K0071+370 - K0071+494; CHAINAGE 24384 - CHAINAGE 24508; (2) K0080+438 - K0080+663; CHAINAGE 33449 - CHAINAGE 33674; (3) K0101+091 - K0101+253; CHAINAGE 5

REHABILITATION OF TOLEDO-TABUELAN-SAN REMEGIO ROAD (INTERMITTENT SECTION) WITH SLIPS, LOCATED AT (1) K0071+370 - K0071+494; CHAINAGE 24384 - CHAINAGE 24508; (2) K0080+438 - K0080+663; CHAINAGE 33449 - CHAINAGE 33674; (3) K0101+091 - K0101+253; CHAINAGE 5 is a DPWH-tracked public work in Cebu 3rd DEO, Region VII. Reported contract value: ₱46,521,740.84. Status: Reported complete (DPWH). Contractor on record: HI-TRI DEVELOPMENT CORP. Figures trace to dpwh.

Cebu 3rd DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Combado River - Himungbongan Flood Control Structures, Sitio Combado, Brgy. Cantu - od, Balamban, Cebu
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-16-0022690

₱14,409,557.00 · FY2016

Released to Mariano Marcos Memorial Hospital and Medical CTo (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

61 projects · ₱3.1B total · 0 flags

4. Implementation

Contract Amount

₱46,521,740.84

Progress

Reported complete (DPWH)

Start Date

February 3, 2016

Target End

January 12, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.