Flood Control and Drainage21GL0078

CONSTRUCTION OF GUINTUBHAN RIVER BANK SLOPE PROTECTION (DOWNSTREAM OF GUINTUBHAN BRIDGE) ALONG BINALBAGAN - ISABELA ROAD (LEFT BANK), NEGROS OCCIDENTAL

CONSTRUCTION OF GUINTUBHAN RIVER BANK SLOPE PROTECTION (DOWNSTREAM OF GUINTUBHAN BRIDGE) ALONG BINALBAGAN - ISABELA ROAD (LEFT BANK), NEGROS OCCIDENTAL is a DPWH-tracked public work in Negros Occidental 2nd DEO, Negros Island Region. Reported contract value: ₱29,399,963.45. Status: Reported complete (DPWH). Contractor on record: LEGACY CONST CORP FORMERLY: LEGACY CONST 22465. Figures trace to dpwh.

Negros Occidental 2nd DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱47,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of River Flood Control and Slope Protection Structures along Tibsok River (Guimaras Strait As An Outfall), Sta. 0+000 - Sta. 0+400 (Left Side Facing Downstream) (Section I) San Enrique, Negros Occidental
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-D-21-0006918

₱1,012,525.00 · FY2021

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 22465

997 projects · ₱51.2B total · 0 flags

Other projects by this contractor

No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD AND CAUSEWAY, BRGY. CAMBAJAO-BRGY. ALIBAGON, CAJIDIOCAN, SIBUYAN ISLAND, ROMBLON

Region IV-B, Region IV-B

2024₱297.0M
Past target date (DPWH On-Going)

SUSTAINABLE INFRASTRUCTURE PROECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG CARMEN PORT, SAN AGUSTIN, ROMBLON

Region IV-B, Region IV-B

2023₱289.5M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG SAN JOSE PORT, ROMBLON

Region IV-B, Region IV-B

2023₱289.5M
Past target date (DPWH On-Going)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG MONGPONG, BRGY. STA. LUCIA, SABLAYAN, OCC. MINDORO

Region IV-B, Region IV-B

2024₱289.5M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUSUANGA RIVER, BRGY. CENTRAL-BRGY. SAN AGUSTIN, STA. 000+240-STA. 000+735.5 (LEFT SIDE), SAN JOSE, OCC. MIND

Region IV-B, Region IV-B

2025₱284.2M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUSUANGA RIVER, BRGY. BATASAN, STA. 000+000-STA. 000+473.35, SAN JOSE, OCC. MINDORO

Region IV-B, Region IV-B

2025₱284.2M
Past target date (DPWH On-Going)
View all 997 projects →

4. Implementation

Contract Amount

₱29,399,963.45

Progress

Reported complete (DPWH)

Start Date

October 11, 2021

Target End

April 19, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.