Flood Control and Drainage18IG0007

REHABILITATION/IMPROVEMENT OF FLOOD CONTROL STRUCTURES, SALOG RIVER BASIN (SALOG BRIDGE APPROACH A), HILONGOS, LEYTE 5TH LD

REHABILITATION/IMPROVEMENT OF FLOOD CONTROL STRUCTURES, SALOG RIVER BASIN (SALOG BRIDGE APPROACH A), HILONGOS, LEYTE 5TH LD is a DPWH-tracked public work in Leyte 5th DEO, Region VIII. Reported contract value: ₱29,400,000.00. Status: Reported complete (DPWH). Contractor on record: RJIR ENT CORP. Figures trace to dpwh.

Leyte 5th DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Improvement of Flood Control Structures, Salog River Basin (Salog Bridge Approach B), Hilongos, Leyte
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Agency-level releases for FY2018, not tied to this contract

Leyte 5th DEO · SARO 1,489 (₱126,676,811,675.00) · NCA 1,617 (₱426,584,627,343.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

692 projects · ₱17.7B total · 35 flags

Other projects by this contractor

View all 692 projects →

4. Implementation

Contract Amount

₱29,400,000.00

Progress

Reported complete (DPWH)

Start Date

March 4, 2018

Target End

September 29, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.