Flood Control and Drainage20OI0110

CONSTRUCTION OF SLOPE PROTECTION AT PASONG BAKA CREEK, BRGY. TALON 5, LAS PINAS CITY

CONSTRUCTION OF SLOPE PROTECTION AT PASONG BAKA CREEK, BRGY. TALON 5, LAS PINAS CITY is a DPWH-tracked public work in Las Piñas-Muntinlupa DEO, National Capital Region. Reported contract value: ₱67,540,977.55. Status: Reported complete (DPWH). Contractor on record: I&E CONST CORP FORMERLY: I&E CONSTR 10410. Figures trace to dpwh.

Las Piñas-Muntinlupa DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXI-20-0008456

₱735,991.00 · FY2020

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 10410

154 projects · ₱10.3B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF MISSING LINKS/ NEW ROADS GENERAL NAKAR - DINGALAN ROAD (GEN. NAKAR SIDE), PACKAGE A, QUEZON

Region IV-A, Region IV-A

2022₱289.3M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAMSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)IMUS-BACOOR LINK ROAD, PACKAGE 1, BACOOR, CAVITE

Region IV-A, Region IV-A

2025₱280.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAMSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)IMUS-BACOOR LINK ROAD, PACKAGE 2, BACOOR, CAVITE

Region IV-A, Region IV-A

2025₱280.7M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURES AND OTHER IMPROVEMENTS AT BARANGAYS TALON 1 TO TALON 3, LAS PINAS CITY

Las Piñas-Muntinlupa DEO, National Capital Region

2025₱218.3M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF BASUD-LANOT ROAD, BASUD,

Region V, Region V

2024₱187.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF DAET-SAN VICENTE-SAN LOR

Region V, Region V

2024₱183.3M
Past target date (DPWH On-Going)
View all 154 projects →

4. Implementation

Contract Amount

₱67,540,977.55

Progress

Reported complete (DPWH)

Start Date

October 19, 2020

Target End

February 20, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.