Roads23HE0146

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION ROADS IN BRGY. LAWAAN II, TALISAY, CEBU

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION ROADS IN BRGY. LAWAAN II, TALISAY, CEBU is a DPWH-tracked public work in Cebu 1st DEO, Region VII. Reported contract value: ₱4,945,000.00. Status: Reported complete (DPWH). Contractor on record: APEX BARI CONST CORP. Figures trace to dpwh.

Cebu 1st DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Magsa-ubay Bridge, Section 1 and 2, Sta. 000 + 000 - Sta. 000 + 306, Daanbantayan, Cebu
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-23-0026746

₱94,363.00 · FY2023

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱4,945,000.00

Progress

Reported complete (DPWH)

Start Date

May 17, 2023

Target End

June 20, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.