Roads24IJ0099

CSSP: CONSTRUCTION OF ROAD, BRGY. SAN AGUSTIN - BRGY. HINOGACAN ROAD, GANDARA, SAMAR

CSSP: CONSTRUCTION OF ROAD, BRGY. SAN AGUSTIN - BRGY. HINOGACAN ROAD, GANDARA, SAMAR is a DPWH-tracked public work in Samar 1st DEO, Region VIII. Reported contract value: ₱20,732,514.22. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: 5GG CONST FORMERLY: 5G GALVEZ CONST AND SUPPLY 34736. Figures trace to dpwh.

Samar 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Brgy. San Luis, Pagsanghan, Samar
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXII-24-0019554

₱3,782,550.00 · FY2024

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 34736

44 projects · ₱1.8B total · 0 flags

Other projects by this contractor

No sat.

NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - PANGPANG - PALAPAG - MAPANAS - GAMAY - LAPINIG RD - K0835+554 - K0836+060, K0836+160 - K0836+220, K0836+260 - K0837+750, K0838+000 - K0839+090, K0839+660 - K0839+800, K0839+965 - K0840+052.50, NORTHE

Region VIII, Region VIII

2023₱193.0M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TOURISM DESTINATIONS - ACCESS ROAD LEADING TO PINIPISAKAN FALLS, LAS NAVAS, NORTHERN SAMAR

Region VIII, Region VIII

2022₱158.7M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TRIP) - ACCESS ROAD LEADING TO PINIPISAKAN FALLS, LAS NAVAS, NORTHERN SAMAR

Region VIII, Region VIII

2023₱152.5M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TRIP) - ACCESS ROAD LEADING TO PINIPISAKAN FALLS, LAS NAVAS, NORTHERN SAMAR

Region VIII, Region VIII

2024₱145.8M
Past target date (DPWH On-Going)
No sat.

CONCRETING OF BRGY. MABINI-VICTORY ROAD (ALONG LAS NAVAS-MATUGUINAO ROAD) PHASE 3, BRGY. MABINI-TAYLOR-VICTORY-EL EMPON-POPONTON-CUENCO ROAD, LAS NAVAS, NORTHERN SAMAR

Northern Samar 2nd DEO, Region VIII

2024₱97.9M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, ACCESS ROAD LEADING TO PINIPISAKAN FALLS, SAN ISIDRO, LAS NAVAS, NORTHERN SAMAR

Northern Samar 2nd DEO, Region VIII

2020₱88.2M
Reported complete (DPWH)
View all 44 projects →

4. Implementation

Contract Amount

₱20,732,514.22

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

October 30, 2024

Target End

June 22, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.