CONSTRUCTION OF 1-UNIT 2 STOREY ICT LABORATORY BUILDING MAGLAMBING INTEGRATED SECONDARY SCHOOL (500324) TAGBINA, SURIGAO DEL SUR

CONSTRUCTION OF 1-UNIT 2 STOREY ICT LABORATORY BUILDING MAGLAMBING INTEGRATED SECONDARY SCHOOL (500324) TAGBINA, SURIGAO DEL SUR is a DPWH-tracked public work in Surigao del Sur 2nd DEO, Region XIII. Reported contract value: ₱9,128,417.06. Status: Reported complete (DPWH). Contractor on record: MARK ANTHONY CONST. Figures trace to dpwh.

Surigao del Sur 2nd DEO, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱9,128,417.06

Progress

Reported complete (DPWH)

Start Date

January 23, 2018

Target End

August 1, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.