Flood Control and Drainage20DJ0050

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF RCBC WITH LATERAL DRAINAGE ALONG MSR DAANG MAHARLIKA, K0097+780, TIAONG, QUEZON

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF RCBC WITH LATERAL DRAINAGE ALONG MSR DAANG MAHARLIKA, K0097+780, TIAONG, QUEZON is a DPWH-tracked public work in Quezon 2nd DEO, Region IV-A. Reported contract value: ₱14,699,996.52. Status: Reported complete (DPWH). Contractor on record: ROMHEAD S J BUILDERS AND DEVELOPMENT INC. Figures trace to dpwh.

Quezon 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱2,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures (Slope Protection), Brgy. Masalukot II, Candelaria
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVB-20-0012989

₱309,631.00 · FY2020

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

181 projects · ₱3.1B total · 0 flags

Other projects by this contractor

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF BANTILAN RIVER FLOOD CONTROL (PACKAGE 2), SARIAYA

Quezon 2nd DEO, Region IV-A

2024₱144.8M
Reported complete (DPWH)

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/ FACILITIES, CONSTRUCTION OF DUMACAA RIVER FLOOD CONTROL (PACKAGE 10), LUCENA CITY, QUEZON

Quezon 2nd DEO, Region IV-A

2023₱96.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF QUEZON INDUSTRIAL HIGHWAY (

Quezon 2nd DEO, Region IV-A

2023₱96.5M
Reported complete (DPWH)

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT LAGNAS RIVER (LAGNAS B

Quezon 2nd DEO, Region IV-A

2024₱96.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF QUEZON INDUSTRIAL HIGHWAY

Quezon 2nd DEO, Region IV-A

2025₱94.5M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - GUMACA-PITOGO-MULANAY-SN NARCISO RD - K0232+379 - K0233+700, K0234+371 - K0236+ 850, K0237+789 - K0238+200

Quezon 3rd DEO, Region IV-A

2025₱93.6M
Past target date (DPWH On-Going)
View all 181 projects →

4. Implementation

Contract Amount

₱14,699,996.52

Progress

Reported complete (DPWH)

Start Date

February 17, 2020

Target End

November 27, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.