Buildings and Facilities22FO0070

CONSTRUCTION OF EVACUATION CENTER, SAN JOSE E/S, BRGY. SAN JOSE, LIBON, ALBAY

CONSTRUCTION OF EVACUATION CENTER, SAN JOSE E/S, BRGY. SAN JOSE, LIBON, ALBAY is a DPWH-tracked public work in Albay 3rd DEO, Region V. Reported contract value: ₱6,707,587.99. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: ALPHARD PRIMECON CONST. Figures trace to dpwh.

Albay 3rd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of San Jose Flood Control Structure, San Jose, Libon, Albay
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-22-0000473

₱358,196.00 · FY2022

Released to Biriran National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱6,707,587.99

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 10, 2022

Target End

September 5, 2022

5. Audit