Roads25KM0047

CONCRETING OF ZONE 4 TO ZONE 6, BRGY. BUNAWAN FMR, BRGY. BUNAWAN, ILIGAN CITY, LANAO DEL NORTE

CONCRETING OF ZONE 4 TO ZONE 6, BRGY. BUNAWAN FMR, BRGY. BUNAWAN, ILIGAN CITY, LANAO DEL NORTE is a DPWH-tracked public work in Iligan City DEO, Region X. Reported contract value: ₱14,775,831.64. Status: Past target date (DPWH On-Going). Contractor on record: AJJ STRUKTURE BUILDERS INC 40356. Figures trace to dpwh.

Iligan City DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Ubaldo Laya Flood Control, Brgy. Ubaldo Laya, Iligan City, Lanao del Norte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-25-0017562

₱-1,460,337.00 · FY2025

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱14,775,831.64

Progress

Past target date (DPWH On-Going)

Start Date

June 10, 2025

Target End

October 20, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.