Construction of Revetment20LB0244

Construction of Revetment along Davao River, Bolton Bridge Upstream, S.I.R. New Matina, Ph 1, Sandawa Main Drain Section, Right Bank, Davao City

Construction of Revetment along Davao River, Bolton Bridge Upstream, S.I.R. New Matina, Ph 1, Sandawa Main Drain Section, Right Bank, Davao City is a DPWH-tracked public work in DAVAO DEL SUR, Region XI. Reported contract value: ₱19,600,000.00. Status: Reported complete (DPWH). Contractor on record: LEGACY CONST CORP FORMERLY: LEGACY CONST. Figures trace to sumbong.

DAVAO DEL SUR, Region XI
Region: Region XI

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱46,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Revetment - Davao River Flood Control, Bolton Bridge Upstream, S.I.R New Matina Phase 1 Section, Right Bank, Davao City
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROI-20-0006704

₱1,437,596.00 · FY2020

Released to Davao City District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-20-0014747

₱20,000,000.00 · FY2020

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-20-0015899

₱16,894,000.00 · FY2020

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROXI-20-0018118

₱1,598,382.00 · FY2020

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-20-0014937

₱757,251,000.00 · FY2020

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROXI-20-0006957

₱140,000.00 · FY2020

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROXI-20-0007504

₱35,000.00 · FY2020

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROXI-20-0018349

₱33,947.00 · FY2020

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROXI-20-0006956

₱1,381,000.00 · FY2020

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-20-0014857

₱140,665,000.00 · FY2020

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

1,112 projects · ₱59.5B total · 113 flags

Other projects by this contractor

No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD AND CAUSEWAY, BRGY. CAMBAJAO-BRGY. ALIBAGON, CAJIDIOCAN, SIBUYAN ISLAND, ROMBLON

Region IV-B, Region IV-B

2024₱297.0M
Past target date (DPWH On-Going)

SUSTAINABLE INFRASTRUCTURE PROECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG CARMEN PORT, SAN AGUSTIN, ROMBLON

Region IV-B, Region IV-B

2023₱289.5M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG SAN JOSE PORT, ROMBLON

Region IV-B, Region IV-B

2023₱289.5M
Past target date (DPWH On-Going)

Construction of Dubduban Flood Control Structure, San Agustin, Tablas Island Romblon

ALCANTARA (ROMBLON), ROMBLON, Region IV-B

2023₱289.5M
Reported complete (DPWH)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG MONGPONG, BRGY. STA. LUCIA, SABLAYAN, OCC. MINDORO

Region IV-B, Region IV-B

2024₱289.5M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUSUANGA RIVER, BRGY. CENTRAL-BRGY. SAN AGUSTIN, STA. 000+240-STA. 000+735.5 (LEFT SIDE), SAN JOSE, OCC. MIND

Region IV-B, Region IV-B

2025₱284.2M
Past target date (DPWH On-Going)
View all 1,112 projects →

4. Implementation

Contract Amount

₱19,600,000.00

Progress

Reported complete (DPWH)

Start Date

December 10, 2020

Target End

October 17, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.