Buildings and Facilities25ND0108

CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE 2, HALL OF JUSTICE, BARANGAY LIBERTAD, BUTUAN CITY, AGUSAN DEL NORTE

CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE 2, HALL OF JUSTICE, BARANGAY LIBERTAD, BUTUAN CITY, AGUSAN DEL NORTE is a DPWH-tracked public work in Butuan City DEO, Region XIII. Reported contract value: ₱9,701,549.05. Status: Past target date (DPWH On-Going). Contractor on record: BN BUILDERS AND CONST SUPPLIES INC FORMERLY BN BUILDERS. Figures trace to dpwh.

Butuan City DEO, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Possible match · score 69%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Multi-Purpose Building, Phase 2, Hall of Justice, Barangay Libertad, Butuan City, Agusan del Norte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-25-0007554

₱26,100.00 · FY2025

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱9,701,549.05

Progress

Past target date (DPWH On-Going)

Start Date

August 7, 2025

Target End

December 4, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.