Roads23PA0220

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, REHABILITATION OF BUCAO ROAD, LA PAZ, ABRA

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, REHABILITATION OF BUCAO ROAD, LA PAZ, ABRA is a DPWH-tracked public work in Abra DEO, Cordillera Administrative Region. Reported contract value: ₱96,478,200.00. Status: Past target date (DPWH On-Going). Contractor on record: MG SAMIDAN CONST. Figures trace to dpwh.

Abra DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-23-0023739

₱68,282.00 · FY2023

Released to 0000000 University of - Southeastern Philippines (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

533 projects · ₱51.8B total · 52 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS/NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN TUBA AND TUBLAY, KAMOG JCT. - CALOT - PAPPA - BAGONG - BALLUAY - TUEL JCT

Cordillera Administrative Region, Cordillera Administrative Region

2022₱289.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS ITOGON - DALUPIRIP - SN MANUEL BDRY ROADKO275+510 -

Cordillera Administrative Region, Cordillera Administrative Region

2021₱279.9M
Reported complete (DPWH)
No sat.

BAGUIO - BONTOC RD - KO347+520 - KO347+577BAUKO, MT. PROVINCE

Cordillera Administrative Region, Cordillera Administrative Region

2022₱241.3M
Reported complete (DPWH)
No sat.

SPECIAL ROAD PROJECT - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239, INSTALLATION OF ROAD SAFETY DEVICES ALONG A. SN FERNANDO AIRPORT RD - K0265 + (-273)-K0265 + (-128) - K0266 + 828-K0267 + 015, BARANGAY PAGDALAGAN. BARANGAY SAN VICENTE, BARANGAY

Region I, Region I

2023₱241.2M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) ALONG GOV. BADO DANGWA NATIONAL RD (S00377LZ) KO328+(-085) - KO329+420, (S00376LZ) KO320+100 - KO3

Cordillera Administrative Region, Cordillera Administrative Region

2022₱212.3M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ROAD, CAMP 1 - TABAAN SUR - TABAAN NORTE - TALOY SUR ROAD TO MARCOS HIGHWAY, TUBA, BENGUET

Cordillera Administrative Region, Cordillera Administrative Region

2022₱212.3M
Reported complete (DPWH)
View all 533 projects →

4. Implementation

Contract Amount

₱96,478,200.00

Progress

Past target date (DPWH On-Going)

Start Date

November 23, 2023

Target End

July 15, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.