GAA 2016 MFO-115K00099

COMPL. OF OPOL BR ALONG BCIR, MIS. OR. 2ND LD

COMPL. OF OPOL BR ALONG BCIR, MIS. OR. 2ND LD is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱118,412,265.91. Status: Reported complete (DPWH). Contractor on record: UKC BUILDERS INC. Figures trace to dpwh.

Region X, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱118,412,265.91

Progress

Reported complete (DPWH)

Start Date

March 7, 2016

Target End

March 11, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.