Roads23E00221

CONCRETING OF SITIO MALUTOK, BRGY. RANSANG FMR, RIZAL, PALAWAN

CONCRETING OF SITIO MALUTOK, BRGY. RANSANG FMR, RIZAL, PALAWAN is a DPWH-tracked public work in Region IV-B, Region IV-B. Reported contract value: ₱14,521,409.88. Status: Past target date (DPWH On-Going). Contractor on record: AR LUSTRE CONST CORP FORMERLY:A R LUSTRE JR CONST. Figures trace to dpwh.

Region IV-B, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

104 projects · ₱5.0B total · 0 flags

4. Implementation

Contract Amount

₱14,521,409.88

Progress

Past target date (DPWH On-Going)

Start Date

September 16, 2023

Target End

December 11, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.