Roads24K00300

REHAB./RECONST./RECONST./UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS SAYRE HIGHWAY - K1529 + 011 - K1530 + 014, K1530 + 633 - K1530 + 889

REHAB./RECONST./RECONST./UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS SAYRE HIGHWAY - K1529 + 011 - K1530 + 014, K1530 + 633 - K1530 + 889 is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱31,002,166.24. Status: Reported complete (DPWH). Contractor on record: M MONTESCLAROS ENT INC 6506. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱31,002,166.24

Progress

Reported complete (DPWH)

Start Date

July 4, 2024

Target End

January 29, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.