Roads19MC0076

RECONSTRUCTION TO CONCRETE PAVEMENT- ALONG MATALAM-M'LANG-BAGONTAPAY RD K1649+030 TO K1650+000, M'LANG, NORTH COTABATO

RECONSTRUCTION TO CONCRETE PAVEMENT- ALONG MATALAM-M'LANG-BAGONTAPAY RD K1649+030 TO K1650+000, M'LANG, NORTH COTABATO is a DPWH-tracked public work in Cotabato 2nd DEO, Region XII. Reported contract value: ₱26,089,715.69. Status: Reported complete (DPWH). Contractor on record: JARGON CONST. Figures trace to dpwh.

Cotabato 2nd DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱26,089,715.69

Progress

Reported complete (DPWH)

Start Date

July 21, 2019

Target End

January 7, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.