GAA 2025 CP25FL0044

CONST/IMPRVT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM RD. INFRA. PROGRAM -)

CONST/IMPRVT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM RD. INFRA. PROGRAM -) is a DPWH-tracked public work in Sorsogon 2nd DEO, Region V. Reported contract value: ₱62,408,386.57. Status: Past target date (DPWH On-Going). Contractor on record: AREMAR CONST CORP. Figures trace to dpwh.

Sorsogon 2nd DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, San Ramon RIS, Bulan, Sorsogon
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROV-25-0015542

₱4,746,264.00 · FY2025

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

161 projects · ₱12.0B total · 2 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS-DAANG MAHARLIKA(LZ), SECTION C:K0585+431-K0588+170.00 (W/ EQUATIONS);SECTION D: SECTION D:K0588+370.00-K0590+181.00(W/ EQUATIONS); SECTION E

Region V, Region V

2018₱289.5M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-CLUSTER II:I-BARCELONA-CASIGURAN DIVERSION ROAD,BARCELONA SECTION,SORSOGON;II-JUBAN-BULAN DIVERSION ROAD,BULAN SECTION,SORSOGON;III-

Region V, Region V

2021₱241.9M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-CLUSTER I-I-SORSOGON CITY COASTAL BYPASS ROAD, PACKAGE 7, SORSOGON;II-SORSOGON CITY COASTAL BYPASS ROAD, PACKAGE 8, SORSOGON, SORSOG

Region V, Region V

2021₱211.5M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, SORSOGON CITY COASTAL BY-PASS ROAD, PACKAGE 6, SORSOGON, SORSOGON CITY, SORSOGON (1ST LEGISLATIVE DISTRICT)

Region V, Region V

2020₱193.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF BALOGO SPORT COMPLEX SORSOGON CITY

Sorsogon DEO, Region V

2020₱192.7M
Reported complete (DPWH)
No sat.

ORGANIZAL OUTCOM 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-SORSOGON CITY COASTAL BYPASS ROAD, PACKAGE 19, SORSOGON

Sorsogon DEO, Region V

2025₱141.4M
Past target date (DPWH On-Going)
View all 161 projects →

4. Implementation

Contract Amount

₱62,408,386.57

Progress

Past target date (DPWH On-Going)

Start Date

May 23, 2025

Target End

March 27, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.