Flood Control and Drainage17HJ0010

CONSTRUCTION OF BATERIA FLOOD CONTROL ALONG DUMAGUETE NORTH ROAD, GUIHULNGAN CITY, NEGROS ORIENTAL

CONSTRUCTION OF BATERIA FLOOD CONTROL ALONG DUMAGUETE NORTH ROAD, GUIHULNGAN CITY, NEGROS ORIENTAL is a DPWH-tracked public work in Negros Oriental 1st DEO, Negros Island Region. Reported contract value: ₱37,227,589.50. Status: Reported complete (DPWH). Contractor on record: QM BUILDERS 30743. Figures trace to dpwh.

Negros Oriental 1st DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 30743

681 projects · ₱40.1B total · 0 flags

Other projects by this contractor

No sat.

CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, BARANGAY MATALAO -BRGY. MANLAPAY, DUMANJUG, CEBU

Region VII, Region VII

2025₱359.4M
Past target date (DPWH On-Going)
No sat.

CSSP, BASIC INFRASTRUCTURE PROGRAM (BIP)-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (NEW MUNICIPAL HALL), POBLACION, DUMANJUG, CEBU

Region VII, Region VII

2024₱313.6M
Past target date (DPWH On-Going)
No sat.

REHABILITATION/RECONST.OF NATIONAL ROADS WITH SLIPS, SLOPE, COLLAPSE, AND LANDSLIDE, SECONDARY ROADS,CEBU TOLEDO WHARF ROADS, CEBU-TOLEDO WHARF ROAD (JCT. NAGA-ULING

Region VII, Region VII

2016₱295.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, ROAD CONCRETING OF SRP BACK ROAD (PHASE III)

Region VII, Region VII

2023₱289.4M
Past target date (DPWH On-Going)
No sat.

MF0-1 NATIONAL ROAD NETWORK SERVICES, ASSET PRESERVATION OF NATIONAL ROADS-REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDES , SECONDARY ROADS, CEBU-TOLEDO WHARF ROAD (JCT. NAGA-ULING,) K0011+237-K0013+245, K0016+50

Region VII, Region VII

2017₱289.0M
Reported complete (DPWH)
No sat.

CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONST. OF ROAD, BARANGAY LIBO-BARANGAY GUIBANGCO-AN, SIBONGA, CEBU PHASE 2

Region VII, Region VII

2025₱283.7M
Past target date (DPWH On-Going)
View all 681 projects →

4. Implementation

Contract Amount

₱37,227,589.50

Progress

Reported complete (DPWH)

Start Date

March 13, 2017

Target End

December 17, 2017

5. Audit