Buildings and Facilities22DF0132

CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP),BIPMULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICESCONSTRUCTION OF MULTI-PURPOSE BUILDING, TROPICAL VILLAGE NATIONAL HIGH SCHOOL, BARANGAY SAN FRANCISCO,GEN TRIAS

CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP),BIPMULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICESCONSTRUCTION OF MULTI-PURPOSE BUILDING, TROPICAL VILLAGE NATIONAL HIGH SCHOOL, BARANGAY SAN FRANCISCO,GEN TRIAS is a DPWH-tracked public work in Cavite 1st DEO, Region IV-A. Reported contract value: ₱4,698,540.64. Status: Reported complete (DPWH). Contractor on record: MONTADEL ENT. Figures trace to dpwh.

Cavite 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Manila Bay, Barangay San Rafael IV, Noveleta, Cavite
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-22-0012874

₱4,197,400.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

38 projects · ₱903.6M total · 2 flags

Other projects by this contractor

Construction of Revetment along Julian River, Barangay Malagasang I-D, West Side, Imus, Cavite

IMUS CITY (CAVITE), CAVITE, Region IV-A

2023₱91.7M
Reported complete (DPWH)
No sat.

Construction of Revetment along Julian River, Brgy. Malagasang II-A, West Side, Imus, Cavite

IMUS CITY (CAVITE), CAVITE, Region IV-A

2022₱90.7M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGRAMCONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMSCONST OF REVETMENT ALONG JULIAN RIVER, BRGY. MALAGASANG 1-F, WEST SIDE

Cavite 1st DEO, Region IV-A

2024₱72.4M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOODMANAGEMENT PROGRAM, CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHINMAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF REVETMENT ALONG IMUS RIVER,

Cavite 1st DEO, Region IV-A

2020₱49.0M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGRAMCONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERSCONSTRUCTION OF REVETMENT ALONG IMUS RIVER,

Cavite 1st DEO, Region IV-A

2021₱49.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAMSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIESCONSTRUCTION OF BRIDGE/VIADUCT AND ROAD A

Cavite 1st DEO, Region IV-A

2025₱47.5M
Past target date (DPWH On-Going)
View all 38 projects →

4. Implementation

Contract Amount

₱4,698,540.64

Progress

Reported complete (DPWH)

Start Date

March 6, 2022

Target End

October 1, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.