GAA 2025 DA FMR25IG0074

CONCRETING OF BRGY. SAN ANTONIO FMR, BRGY. SAN ANTONIO, HILONGOS, LEYTE

CONCRETING OF BRGY. SAN ANTONIO FMR, BRGY. SAN ANTONIO, HILONGOS, LEYTE is a DPWH-tracked public work in Leyte 5th DEO, Region VIII. Reported contract value: ₱14,914,800.00. Status: Past target date (DPWH On-Going). Contractor on record: C N E CONST. Figures trace to dpwh.

Leyte 5th DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱99,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along San Isidro River, Brgy. San Isidro, Sta Fe, Leyte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXI-25-0015824

₱13,769,000.00 · FY2025

Released to Division of Davao City (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱14,914,800.00

Progress

Past target date (DPWH On-Going)

Start Date

June 19, 2025

Target End

November 10, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.