Roads23F00338

CONCRETING OF PUROK 1 TO PUROK 3 BRGY. MAISOG FMR, BRGY. MAISOG, SAN LORENZO RUIZ, CAMARINES NORTE, SAN LORENZO RUIZ, CAMARINES NORTE (2ND LEGISLATIVE DISTRICT)

CONCRETING OF PUROK 1 TO PUROK 3 BRGY. MAISOG FMR, BRGY. MAISOG, SAN LORENZO RUIZ, CAMARINES NORTE, SAN LORENZO RUIZ, CAMARINES NORTE (2ND LEGISLATIVE DISTRICT) is a DPWH-tracked public work in Region V, Region V. Reported contract value: ₱11,939,025.57. Status: Reported complete (DPWH). Contractor on record: JAEJR ELECTRICAL CONST. Figures trace to dpwh.

Region V, Region V
Region: Region V

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱11,939,025.57

Progress

Reported complete (DPWH)

Start Date

September 29, 2023

Target End

January 25, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.