Construction of Flood Mitigation Structure22BD0097

Construction of Cagayan River Flood Control Structure, Natappian, Solana, Cagayan

Construction of Cagayan River Flood Control Structure, Natappian, Solana, Cagayan is a DPWH-tracked public work in SOLANA (CAGAYAN), CAGAYAN, Region II. Reported contract value: ₱19,001,115.52. Status: Reported complete (DPWH). Contractor on record: RPF CONST. Figures trace to sumbong.

SOLANA (CAGAYAN), CAGAYAN, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Cagayan River, Tucalana, Lal-lo, Cagayan
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-22-0007797

₱107,065,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002961

₱218,601,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROII-22-0002541

₱924,015.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROII-22-0002542

₱85,043.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

56 projects · ₱1.1B total · 0 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS; ALCALA-STO. NIÑO-LASAM ROAD, CAGAYAN, CAGAYAN-PACKAGE 2, CAGAYAN

Region II, Region II

2023₱113.3M
Past target date (DPWH On-Going)
No sat.

CSSP: SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD LEADING TO CONVENTION/EXPO AND SPORTS CENTER, DIORA ZINUGAN, STA. ANA, CAGAYAN

Cagayan 1st DEO, Region II

2022₱96.5M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT-IMPROVEMENT/WIDENING OF NATIONAL ROADS - N1; ROAD WIDENING - JCT. LOGAC-MAGAPIT ROAD - K0708+580 - K0711+633.40 BARANGAY ALAGUIA TO BARANGAY MAGAPIT, LAL-LO, CAGAYAN (S00688LZ)

Cagayan 1st DEO, Region II

2017₱91.2M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS- ALCALA-STO. NIÑO- LASAM ROAD

Region II, Region II

2022₱85.6M
Reported complete (DPWH)
No sat.

CONST./MAINTENANCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEMS -CONST. OF FLOOD MITIGATION STRUCTURE- CONST. OF FLOOD CONTROL SYSTEM, STA. 0+000 - STA. 0+348 (DOWNSTREAM), BRGY. CASICALLAN NORTE & AGUIGUICAN, GATTARAN, CAGAYAN

Cagayan 1st DEO, Region II

2018₱66.9M
Reported complete (DPWH)
No sat.

Construction of Drainage System along Caritan- Balzain Creek Sta.0+(-280) - Sta. 0+(-689.20), Caritan, Tuguegarao City, Cagayan

TUGUEGARAO CITY (CAPITAL) (CAGAYAN), CAGAYAN, Region II

2022₱57.9M
Reported complete (DPWH)
View all 56 projects →

4. Implementation

Contract Amount

₱19,001,115.52

Progress

Reported complete (DPWH)

Start Date

March 28, 2022

Target End

March 13, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.