Water Provision and Storage22JD0050

CONSTRUCTION (COMPLETION) OF WATER SYSTEM BARANGAY LIBAY, SIBUTAD,ZN

CONSTRUCTION (COMPLETION) OF WATER SYSTEM BARANGAY LIBAY, SIBUTAD,ZN is a DPWH-tracked public work in Zamboanga del Norte 1st DEO, Region IX. Reported contract value: ₱3,930,490.36. Status: Reported complete (DPWH). Contractor on record: THREE K CONST AND ENT INC. Figures trace to dpwh.

Zamboanga del Norte 1st DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱40,620,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Dicayo River (Downstream), Barangay Dos, Katipunan, Zamboanga del Norte (Package 1)
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-C-22-0016012

₱1,665,124,014.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

66 projects · ₱427.0M total · 0 flags

4. Implementation

Contract Amount

₱3,930,490.36

Progress

Reported complete (DPWH)

Start Date

February 24, 2022

Target End

June 3, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.